Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : Chinnasalem-Kallakurichi New Line (MM of cuddalore- Salem 191 KM).

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
417.50419.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
28.33171.37-15.38184.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202512/202412/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
99.030

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Blanketing, ROB, Ballast collection, S&T works, station building and track linking are in progress.Earthwork, blanketing and track linking are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks