Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : CHENNAI BEACH-CHENNAI EGMORE (4.3 KM) (UMBRELLA WORK PB#57/2019-20/NR).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
359.6274.2310

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
146.512.48143.13302.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20262/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.220

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

Section commissionedAll works are progressing.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks