Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : CHENNAI BEACH-CHENNAI EGMORE (4.3 KM) (UMBRELLA WORK PB#57/2019-20/NR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
359.6274.2274.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
146.5101.544.44252.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20262/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
143.59118.29

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

All works completed. CRS Inspection done on 09.03.2025 and CRS authorized the section on 09.03.2025.All works are progressing.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone