Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : CHENNAI BEACH-CHENNAI EGMORE (4.3 KM) (UMBRELLA WORK PB#57/2019-20/NR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -18

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
359.6274.2274.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0130.3616.14146.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20266/20249/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
126.7180

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information

All works are progressing.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks