Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : BAHRAICH SRAVASTI BALRAMPUR (TULSIPUR).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4939.7804939.78

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1079.635.09220.291334.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20300/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3900

Ministry Review Date

LatestLastPhysical Progress (%)Status
7.5Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Mar-28TDC for commissioning of the project Mar-27

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks