Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : KATIHAR-KUMEDPUR AND KATIHAR-MUKURIA (64.5 KM) (UMBRELLA WORK PB#57/2019-20/NR).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7450942.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0280.156.73336.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20270/08/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
339.720

Ministry Review Date

LatestLastPhysical Progress (%)Status
35Ongoing

Monthly Status

Background Information

Katihar – Kuretha (11.28 Km):- Minor Br. No. 2 & 3B in progress. 75% earth work in KIR-MIYN & 50% of earthwork in MIYN-KUQ done. Major Br. No. 4 – Sheet-piling and pipe cap of A1 & A2 completed. FOB at MIYN & KUQ: Main trestle already erected. Assembly of girders completed. Station Building: Station Buildings at MIYN – Structure, block walls, plaster & roof of mumty completed. Station Buildings at KUQ – 2nd floor roof slab cast, block work and finishing work in progress. Katihar-Sonaili (16.76 Km):- LA of 17.097 Ha (phase-I) completed. Minor Br. No. 11A & 2 – Box-pushing completed and Br. No. 1, 2, 6B & 11A – Balance work in progress. Major Br. No. 3 – Sub Structure completed. Br. No. 5 – Piling in progress. Br. No. 6 – Foundation completed, Sub Structure completed. Br. No. 7 – A1 Foundation completed. Br. No. 8 – Piling completed, pile cap-P1, P2 completed. Br. No. 9 – Piling in progress. Br. No. 10 – Pile cap-P2 completed. Br. No. 11 – Piling in progress. 85% earth work in KIR-DNQ & 75% earth work in DNQ - SI completed. FOBs at DNQ & SI – Flooring & roof sheeting completed. KUQ-Kumedpur (18.25 Km): Major Br. No. 5, 9 & 12 piling completed and Pile cap of A2, P2 & P3 of Br No. 5 completed, Pile cap of A1, A2 & P2 of Br. No. 9 completed, Pile cap of A1 completed in Br. No. 12. Important Br. No. 11 – A1, P2, P5 & 6 – Well foundation completed & Shaft/abutment in progress. Station building at LAV – finishing work in progress. Sonaili –Mukuria (17.85 Km) – Earth work in progress (9%) Important Br. No. 16 – A1 – well sinking completed, P1 – well completed and pier shaft in progress, P2 – well cap completed, P3, P4, P5, P6 – well sinking in progress, P7 – Bottom plugging completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks