Katihar – Kuretha (11.28 Km):-
Minor Br. No. 2 & 3B in progress. 75% earth work in KIR-MIYN & 50% of earthwork in MIYN-KUQ done. Major Br. No. 4 – Sheet-piling and pipe cap of A1 & A2 completed.
FOB at MIYN & KUQ: Main trestle already erected. Assembly of girders completed.
Station Building: Station Buildings at MIYN – Structure, block walls, plaster & roof of mumty completed. Station Buildings at KUQ – 2nd floor roof slab cast, block work and finishing work in progress.
Katihar-Sonaili (16.76 Km):- LA of 17.097 Ha (phase-I) completed.
Minor Br. No. 11A & 2 – Box-pushing completed and Br. No. 1, 2, 6B & 11A – Balance work in progress.
Major Br. No. 3 – Sub Structure completed. Br. No. 5 – Piling in progress. Br. No. 6 – Foundation completed, Sub Structure completed. Br. No. 7 – A1 Foundation completed. Br. No. 8 – Piling completed, pile cap-P1, P2 completed. Br. No. 9 – Piling in progress. Br. No. 10 – Pile cap-P2 completed. Br. No. 11 – Piling in progress.
85% earth work in KIR-DNQ & 75% earth work in DNQ - SI completed.
FOBs at DNQ & SI – Flooring & roof sheeting completed.
KUQ-Kumedpur (18.25 Km): Major Br. No. 5, 9 & 12 piling completed and Pile cap of A2, P2 & P3 of Br No. 5 completed, Pile cap of A1, A2 & P2 of Br. No. 9 completed, Pile cap of A1 completed in Br. No. 12. Important Br. No. 11 – A1, P2, P5 & 6 – Well foundation completed & Shaft/abutment in progress.
Station building at LAV – finishing work in progress.
Sonaili –Mukuria (17.85 Km) – Earth work in progress (9%)
Important Br. No. 16 – A1 – well sinking completed, P1 – well completed and pier shaft in progress, P2 – well cap completed, P3, P4, P5, P6 – well sinking in progress, P7 – Bottom plugging completed.
| |