Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : ROURKELA-BONDAMUNDA A-CABIN 5TH LINE (10 KM) (UMBRELLA WORK PB#57/2019-20/NR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   16.8

Time Overrun (Months)-    -7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
209.750244.99

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3.3751.91.5355.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20260/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4567

Ministry Review Date

LatestLastPhysical Progress (%)Status
10Ongoing

Monthly Status

Background Information

DPR of Rs.244.99 cr has been sanctioned by Railway Board vide letter No. 2021/W-II/SER/DL/(DPR)/15/(e-office No. 3356159) dt. 26.09.2022. All tender awarded. Civil works under progress. Encroachment (200 Nos. Hut) at ROB 133A to be removed, then construction of ROB can be done. For shifting of encroachment discussion and meetings are being held with RSPDPR of Rs.244.99 cr has been sanctioned by Railway Board vide letter No. 2021/W-II/SER/DL/(DPR)/15/(e-office No. 3356159) dt. 26.09.2022. Tender awarded on 19.12.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone