Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 16.8
|
Time Overrun (Months)-
-7
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
DPR of Rs.244.99 cr has been sanctioned by Railway Board vide letter No. 2021/W-II/SER/DL/(DPR)/15/(e-office No. 3356159) dt. 26.09.2022. All tender awarded. Civil works under progress. Encroachment (200 Nos. Hut) at ROB 133A to be removed, then construction of ROB can be done. For shifting of encroachment discussion and meetings are being held with RSP | DPR of Rs.244.99 cr has been sanctioned by Railway Board vide letter No. 2021/W-II/SER/DL/(DPR)/15/(e-office No. 3356159) dt. 26.09.2022. Tender awarded on 19.12.2023. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |