Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : Gauge conversion of Raipur(Kendri)-Dhamtari and Abhanpur-Rajim branch (67.20 km).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1171.301171.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
560.4557.240617.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20240/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
118.9118.9

Ministry Review Date

LatestLastPhysical Progress (%)Status
82Ongoing

Monthly Status

Background Information

Kendri- Abhanpur-6 Km & Abhanpur-Rajim 17.30 Km , Total 23.30 Km upto june-25 completed and commissioned,work is in progress in Balance section Abhanpur-Kurud & Kurud Dhamtari total 43.90 Km.Kendri- Abhanpur-6 Km section commissioned on 6.2.24. work is in progress in entire section.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks