Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : NIPANIA-BHATAPRA (14.4 KM) 4TH LINE (PB#72/NR/2022-23).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
170.490170.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.12.010.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20260/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
49.1749.17

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

EPC tender awarded and work is in progress.Nipania- Bhatapara (14.40 Km) 4th line sanctioned by Railway Board on 8.12.22 at the cost of Rs. 170.49 Cr. EPC tender awarded and work yet to start

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks