Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : 4TH LINE - BHILAI-BHILAI NAGAR (8.8 KM) (PB#72/NR/2022-23).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   4.9

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
169.060177.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0.020.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20260/09/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100100

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Bhilai-Bhilainagar (8.8 Km) 4th line sanctioned on 30.9.2022 at the cost of Rs. 177.34 Cr. EPC TENDER awarded and work yet to start.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone