Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : 4TH LINE - RAJNANDGAON-DONGARHGARH (31.2 KM) (PB#72/NR/2022-23).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
328.340328.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12.79.5623.336.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20260/09/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
102.81102.81

Ministry Review Date

LatestLastPhysical Progress (%)Status
20Ongoing

Monthly Status

Background Information

Earth work, Major bridge and minor bridge is in progress.Rajnandgaon- Dongargarh (31.20 Km) 4th line sanctioned by Railway Board on 12.9.22 at the cost of Rs. 328.34 Cr.EPC tender awarded and work yet to start.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks