Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : DOUBLING OF BORIDAND - AMBIKAPUR ( SURAJPUR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1376.20775.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
018.8511.6530.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20300/06/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
800

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Detailed estimate of Boridand- Surajpur (79.90 Km)sanctioned by Railway Board on 8.6.22.EPC tender from Baikunthpur-Surajpur section (37.40 Kms) awarded and work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone