Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : DOUBLING OF BORIDAND - AMBIKAPUR ( SURAJPUR).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1376.21242.941242.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
154.634.2534.91193.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20300/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
35.235.2

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

Surajpur- Baikunthpur (40 Km) work is in progress. Baikunthpur- Boridand EPC tender invited.Detailed estimate of Boridand- Surajpur (79.90 Km)sanctioned by Railway Board on 8.6.22.EPC tender from Baikunthpur-Surajpur section (37.40 Kms) awarded and work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks