Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
7
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Progress during Mar’25:
FOB at Gill station: FOB Main Girder Deck slab casting completed. 1 no. staircase flight casting completed. Bracing of Main girder completed.
119 cum earthwork & 1366 cum blanketing has been done.
Erection of 1 no. height gauge & reverse ramps casting has been completed at LHS 7C.
Painting, door fixing, sanitary fitting works for toilet blocks at platforms & resting facility for machine staff at Gill has been completed.
102 cum ballast has been supplied.
1.17 Tkm ballast spreading has been supplied in LDH-Gill section.
1.105 Tkm sleeper laying has been completed in LDH-GILL Section.
0.339 Tkm Track linking has been completed in LDH-GILL section.
1.26 Tkm Rail painting has been completed in LDH-GILL section.
FB Welding has been completed in LDH-GILL section.
05 nos, switch assembly, 50 nos. glued joints & 03 nos. SEJ assembly has been completed in LDH-Gill section.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |