Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : VIJAYAWADA KAZIPET BYEPASS LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
226.720226.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
89.38114.8523.83228.06

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

BYPASS AT VIJAYAWADA This involves construction of 2 ROR at ch 4347 Br No 784B ( 1x6.1 PSC + 2 x 91.4 OWG + 1x6.1 PSC ) & at ch 18697 Br No 8B ( 2x18.3 PSC + 1x91.4OWG + 2x18.3 PSC ). Tender finalized on 14.11.2022. 3 Stations at VNC ( Ch 10.1Km ) , Gundala ( Ch 14.997 Km) , Mustabad ( Ch 21.67 Km ). Total land Required :26.73 Ha , Acquired : 18.29 Ha , Balance : 8.44 Ha Land Acquisition award passed for 23.125 Ac land in Gollapudi village between VNC-RYP. Amount disbursements in progress. Total 189 Cr deposited towards LA.BZA North cabin – Gunadala (5.01Km): (6.0 Km Commissioned on 22.09.2023 , Gunadala -Mustabad 6.55 Feb-25, Rayanapadu - BZA North cabin 10.02 Mar-25. BYPASS AT KAZIPET- The byepass line to take off from existing DN Loop line of HSP yard and run parallel to Exg. Dn. Main line up to km. 362.275 and cross below existing DN and UP lines through proposed RCC Box of 6.5m X 7.5m X 340m (Rail under Rail arrangement) and then run parallel to Up main line to join KZJ Town station. CRS inspection done on 19.09.2024 & 20.09.2024. CRS authorization received on 19.10.2024 and commissioned. (Diversion work with Cut & cut & connection (length 1.027Km) completed in April -2024Modified DE for new bye pass alignment (Rail Over Rail) for Rs.495.51 Crs sanctioned by RB vide letter 14/01/2019. BYPASS AT VIJAYAWADA This involves construction of 2 ROR at ch 4347 Br No 784B ( 1x6.1 PSC + 2 x 91.4 OWG + 1x6.1 PSC ) & at ch 18697 Br No 8B ( 2x18.3 PSC + 1x91.4OWG + 2x18.3 PSC ). Tender finalized on 14.11.2022. 3 Stations at VNC ( Ch 10.1Km ) , Gundala ( Ch 14.997 Km) , Mustabad ( Ch 21.67 Km ). Total land Required :26.73 Ha , Acquired : 18.29 Ha , Balance : 8.44 Ha BZA North cabin – Gunadala (5.01Km): (6.0Km Commisssioned on 22.09.2023 , Gunadala -Mustabad 6.55 May-24, Rayanapadu - BZA North cabin 10.02 Jun-24. BYPASS AT KAZIPET- Detailed estimate sanctioned for an amount of 125.14 Cr. This bye pass line is lying between Hasanparthi Road and KazipetTown. Major Br.No.8 completed between Gunadala – Mustabad

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone