Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1. Gooty Bypass line work: (3.17 Km ) Commissioned on 27.11.2022 CRS authorisation obtained on 26.11.2022 for 40 Kmph on Bypass line. PCEE authorisation obtained on 27.11.2022. One new halt station (Gooty Fort station) with 550m. high level platform was constructed on the bypass line connecting Gooty - Dharmavaram line to Gooty - Renigunta lines.
2. Wadi Byepass : One end of take off from Sulehalli (SC division) &other end from Nalwar end of GTL division. Earth work completed. Minor bridges 18 out of 18 completed. All 4 Major Bridges completed. Protective works in progress. Ballast supply completed. Commissioning of Sulehalli West and Nalwar North New Station in progress and CRS Inspection completed on 12.03.25 for a length of 24.05 Km.
3. Renigunta Byepass :
(i) (i) As the construction of NL by RVNL connecting Obulapuram on GTL-RU section with Venkatachalam on BZA-GDR section is commissioned, the doubling of Byepass connecting GDR-GY lines is not necessary.
(ii) MAS-TPTY Bye pass: Land acquisition request submitted to district Collector/Chittoor on 28.02.2018. Land acquisition is required in Built up area. Joint survey with revenue Dept. completed. ¿.3.50 Cr deposited to RDO/TPTY in Aug-21, Rs 5.08 Cr paid on 08.09.2022 for Land acquisition including R&R package. Again Rs. 14.25 Cr deposited for R&R package on 15.12.2023.
(iii) 13000 cum (scope of earthwork = 25000 cum) of earthwork is completed and further work is in progress.
(iv) Construction of Retaining wall on TPTY side is in progress.
(v) Construction of Br.No.1 is completed.
(vi) For bridge No.2 (10X12.20m), 40Nos. PSC girders and 10Nos. Ballast retainers were casted. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |