Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BUDNI-BARKHERA - 3RD LINE (33 KM).

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
991.602097

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
001775.591775.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/202412/202312/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400400

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

This Project is fully completed and commissioned on 09-12-2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks