Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : LUDHIANA MULLANPUR DOUBLING.

Reported Date : 06-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2350235

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2.51.381.245.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Ongoing

Monthly Status

Background Information

Progress during May-25: Mullanpur-Baddowal (10 Km ) doubling commissioned on 12.02.2024. Speed trial between Ludhiana- Baddowal section(11km) conducted on 26.11.2024. Commissioning will be done along with commissioning of Ludhiana - Gill Section (8km) & Ludhiana Yard which is planned in July-25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks