Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : BARABANKI MALHAUR 3RD AND 4TH LINE (32.84 KM).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
323.850407

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
5.17013.7418.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20251/20261/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
55.170

Ministry Review Date

LatestLastPhysical Progress (%)Status
59Ongoing

Monthly Status

Background Information

Progress during Month of Jun’25 : Earthwork in cutting: 810 cum Earthwork in filling: 9208 cum Blanketing work: 4578 cum Slope dressing: 1500 mtr Pile casting: - NIL Pile Cap-01 Nos Ballast Supply: 646 cum Wider sleeper supply: NIL Sleeper Placing: NIL Tree cutting: 98 Nos OHE Foundation: 19 Nos Mast Erection: 53 Nos Grouting: 82 Nos. Muffing : 74 Nos DMA Erection : 13 Nos Boom : 8 Nos

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks