Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : BARABANKI MALHAUR 3RD AND 4TH LINE (32.84 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   25.68

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
323.850407

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
03.61.575.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7097.96

Ministry Review Date

LatestLastPhysical Progress (%)Status
56Ongoing

Monthly Status

Background Information

work status for the Month of March-2025 Earthwork in filling 5115, Earthwork in cutting 14314 and Blanketing 5458 have been completed. 02 nos of minor bridges completed and Retaining wall 86 m have been completed. Piling at Major Bridge 441 completed, 455A completed and 459 is in Progress. Work at RUB 184A: Utility Shifting & Work is in Progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone