Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : DOUBLING BETWEEN JAUNPUR JN-ZAFFARABAD (6.28 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
177.330177.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00.32.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20260/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
165.99

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Status during month of Mar’25: Land acquisition work in progress. Award for 20F is done. Earth work tender done.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone