•Work sanctioned in year2017-18.
•DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22.
•Land acquisition completed, Tender awarded & work is in progress. | •Work sanctioned in year2017-18.
•DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22.
•Earthwork started at Ambaji station.
•For rest of the section tender will be opened
on 19.04.24
• Land acquisition in progress |