Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : TARANGA HILL ABU ROAD VIA AMBAJI NEW LINE.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2798.1602798.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
990.8472.2540.071103.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20300/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6100

Ministry Review Date

LatestLastPhysical Progress (%)Status
12.5Ongoing

Monthly Status

Background Information

•Work sanctioned in year2017-18. •DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22. •Land acquisition completed. •Work is in progress•Work sanctioned in year2017-18. •DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22. •Earthwork started at Ambaji station. •For rest of the section tender will be opened on 19.04.24 • Land acquisition in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks