•Work sanctioned in year2017-18.
•DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22.
•Stage-I clearance Mahesana (0.39 Ha on 04.08.23), Sabarkantha (69.048 Ha on 28.10.23) & Banaskantha (94.621 Ha on 28.10.23). Rs. 284 Cr paid for compensatory afforestation land.
Transfer of land for compensatory afforestation is to be done by Collector, Sabarkantha (69.04 Ha). CA land has been transferred to Forest department on dated 11.02.25.
•Contractor has mobilized machineries for Tunnel work & portal work started.
| •Work sanctioned in year2017-18.
•DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22.
•Earthwork started at Ambaji station.
•For rest of the section tender will be opened
on 19.04.24
• Land acquisition in progress
|