Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : TARANGA HILL ABU ROAD VIA AMBAJI NEW LINE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -43

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1695.8201695.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
25352.27.98378.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20300/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

•Work sanctioned in year2017-18. •DPR costing Rs. 2798.16 Cr., sanctioned by RB on dt. 21.07.22. •Earthwork started at Ambaji station. •For rest of the section tender will be opened on 19.04.24 • Land acquisition in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone