•Phase-I of Dedicated Test Track (0 to 25 km) sanctioned vide PB item No.23 of 2018-2019 with cost of Rs.353.48 Cr. in Dec-2018.
•Track linking done in km 9-13.5, track linking in km 2.5- 9 is in progress. Initial 2.5 km is held up due to delay of acquisition of 28.04Ha land. The NOC from Nation wetland Authority, MoEF&CC. Proposal submitted on 19.01.23, Hydrology report submitted on 3.10.23. Meetings held on 8.12.23, 5.01.24, 6.02.24, 27.02.24. | |