Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : GUDHA THATHANA MITHRI TEST TRACK FOR RDSO.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.480528.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
21571.2116.92303.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
60Ongoing

Monthly Status

Background Information

•Phase-I of Dedicated Test Track (0 to 25 km) sanctioned vide PB item No.23 of 2018-2019 with cost of Rs.353.48 Cr. in Dec-2018. •Track linking done in km 9-13.5, track linking in km 2.5- 9 is in progress. Initial 2.5 km is held up due to delay of acquisition of 28.04Ha land. The NOC from Nation wetland Authority, MoEF&CC. Proposal submitted on 19.01.23, Hydrology report submitted on 3.10.23. Meetings held on 8.12.23, 5.01.24, 6.02.24, 27.02.24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone