Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : GUDHA THATHANA MITHRI TEST TRACK FOR RDSO.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.480500.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
348.053.013.14354.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

•Phase-I of Dedicated Test Track (0 to 25 km) sanctioned vide PB item No.23 of 2018-2019 with cost of Rs.353.48 Cr. in Dec-2018. •Phase-I of Dedicated Test Track work completed.•Phase-I of Dedicated Test Track (0 to 25 km) sanctioned vide PB item No.23 of 2018-2019 with cost of Rs.353.48 Cr. in Dec-2018. •Track linking done in km 9-13.5, track linking in km 2.5- 9 is in progress. Initial 2.5 km is held up due to delay of acquisition of 28.04Ha land. The NOC from Nation wetland Authority, MoEF&CC. Proposal submitted on 19.01.23, Hydrology report submitted on 3.10.23. Meetings held on 8.12.23, 5.01.24, 6.02.24, 27.02.24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <