Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DEDICATED TEST TRACK FOR RDSO (PHASE II).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -23

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
466.420466.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
215193.2810.99419.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20260/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information

•Phase-II of Dedicated Test Track (25 to 59 km) has been sanctioned vide NWR’s Pink Book item No.10 of 2020-21. DPR of this has been approved by Railway Board on 18.11.2021 for Rs. 466.42 Cr. •Tender awarded for formation & bridge work of High speed Loop. Tender awarded for S&T and OHE work for complete project. •Tender awarded for Gudha & Nawa loop. •Alternate alignment of Mithri loop is finalized. 20-E notification for Land acquisition issued on 24.02.2023 and Pvt. Land award declared on 29.07.2023. •Land handed over by State in Feb’24 end. STPs also issued in Feb,24. Site clearance and demarcation is progress. •Efforts shall be made to link Mithri Loop by Mar’25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone