Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-23
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
•Phase-II of Dedicated Test Track (25 to 59 km) has been sanctioned vide NWR’s Pink Book item No.10 of 2020-21. DPR of this has been approved by Railway Board on 18.11.2021 for Rs. 466.42 Cr.
•Tender awarded for formation & bridge work of High speed Loop. Tender awarded for S&T and OHE work for complete project.
•Tender awarded for Gudha & Nawa loop.
•Alternate alignment of Mithri loop is finalized. 20-E notification for Land acquisition issued on 24.02.2023 and Pvt. Land award declared on 29.07.2023.
•Land handed over by State in Feb’24 end. STPs also issued in Feb,24. Site clearance and demarcation is progress.
•Efforts shall be made to link Mithri Loop by Mar’25 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |