Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : JANGHAI-PHAPHAMAU - DOUBLING WITH ELECTRIFICATION (46.79 KM).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
357.480409.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
362.0900362.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

The total Project length is 46.79 Km. Formation work, Major Bridge and minor bridges has been completed in Janghai-BariyaRam-Ugrasenpur Block Section (Phase-I). The work of Track Linking has been started Janghai-BariyaRam-Ugrasenpur Block Section (Phase-I). The work of formation, minor bridges and major bridges for Ugrasenpur-Phulpur-SaraiChandi (Phase-II) & SaraiChandi-Tharwai-Phaphamau (Phase-III) are in full swing. Till date PSC Sleeper 48000nos. have been transported to site out of about 72000 (for which RO issued by NR) . TDC for completion of Janghai-Phaphamau section Doubling is Dec-24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks