Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BHATNI - AUNRIHAR WITH ELECTRIFICATION (125 KM) (EXCL INDARA - MAU (116.95 KM)).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   114.73

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1177.9602529.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
01418.141191537.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/02/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150150

Ministry Review Date

LatestLastPhysical Progress (%)Status
76Ongoing

Monthly Status

Background Information

Total length of the project is 118 km out of which 37.44 km is commissioned as on 31-03-2024. Work is in progress in remaining 80.56 km section. Planning to commission complete project in Feb 2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone