Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : INDORE BUDNI (INDORE JABALPUR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   70.36

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
434007393.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0445.88496.82942.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20300/09/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10801080

Ministry Review Date

LatestLastPhysical Progress (%)Status
11Ongoing

Monthly Status

Background Information

Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone