Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : DALLIRAJHARA - ROWGHAT (95 KM) {PART OF DALLIRAJHARA-JAGDALPUR (235 KM)}.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   157.61

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
631.7801627.56

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
01189.3170.261259.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500500

Ministry Review Date

LatestLastPhysical Progress (%)Status
82Ongoing

Monthly Status

Background Information

Work executed in two phases out of which Phase-1 Dallirajhara-Rowghat-95 Km Executed by RVNL. Dallirajhara- Taroki (76.45 km) was already commissioned. Remaining 18.55 km is planned to commission in June 2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone