Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DOUBLING BETWEEN BHIWANI-DOBH BAHALI.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -26

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
471.060471.06

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11.1353.3213.5177.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20280/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
70110

Ministry Review Date

LatestLastPhysical Progress (%)Status
40Ongoing

Monthly Status

Background Information

•Work sanctioned in year 2022-23 •Cost of work Rs. 471.06 Cr. •DPR sanctioned by Railway Board on 27.02.2023. •The proposed doubling alignment is parallel to existing alignment. Total 0.5339 hectares of Private land is to be acquired. Gazette Notification has been issued on 03.07.2024 and same has been published in Newspaper- Amar-Ujala, dated- 12.07.2024 & Hari Bhumi dated-11.07.2024. 20-E Gazette Notification issued on 05.09.2024 and same has been published in Newspaper- Amar-Ujala, Dainik Bhaskar and Hari Bhumi dated- 15.09.2024. Property survey work is completed by 04.11.24. •Draft Award (20F) has been issued by DRO/ROK on 14.11.2024 for publication in newspaper. Same have been published in newspaper- Amar-Ujala, Dainik Bhaskar, Hari Bhumi & Indian Express on dated- 19.11.2024. Final Award (20F) has been released by DRO/ROK on 20.11.2024. Payment has been released to State authority 16.12.2024. Position of acquired land has been taken over. •Work is in progress. •Work sanctioned in year 2022-23 •Cost of work Rs. 471.06 Cr. •DPR sanctioned by Railway Board on 27.02.2023. •Civil works tender is awarded on 06.11.23. Work is in progress. •Tender for P.way work opened on 02.01.24 & under finalization. •For Ballast supply contract awarded & supply of ballast in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   </