Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DOUBLING BETWEEN BHIWANI-DOBH BAHALI.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
471.060471.06

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
77.9619.1514.29111.4

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20280/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
44Ongoing

Monthly Status

Background Information

•Work sanctioned in year 2022-23 •Cost of work Rs. 471.06 Cr. •DPR sanctioned by Railway Board on 27.02.2023. • Work is in progress•Work sanctioned in year 2022-23 •Cost of work Rs. 471.06 Cr. •DPR sanctioned by Railway Board on 27.02.2023. •Civil works tender is awarded on 06.11.23. Work is in progress. •Tender for P.way work opened on 02.01.24 & under finalization. •For Ballast supply contract awarded & supply of ballast in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks