Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-32
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
•P. way Tender for Churu- Ratangarh (42.81 Kms) is awarded on 11.12.2023 & work is in progress.
•Tender of ballast supply awarded on 21.12.23 & work is in progress.
•Ratangarh - Molisar (18.0 KM) section Commissioned on 31st Jan’25.
| •Work sanctioned in year 2022-23
•Cost of work Rs. 422.60 Cr.
•DPR sanctioned by Railway Board on 03.02.2023.
•Civil works Tender for Ratangarh- Molisar (16.69 Kms) is awarded on 13.07.23 & Work is in
progress.
•Civil Works Tender for Churu- Molisar (26.12
Kms) is awarded on 04.12.2023 & Work is in
progress.
•P.way Tender for Churu- Ratangarh (42.81 Kms)
is awarded on 11.12.2023 & work is in progress.
•Tender of ballast supply awarded on 21.12.23 &
work is in progress.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |