Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DOUBLING BETWEEN CHURU-RATANGARH (42.81 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -32

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
422.60422.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
40.44127.9811.27179.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20280/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
70284.42

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

•P. way Tender for Churu- Ratangarh (42.81 Kms) is awarded on 11.12.2023 & work is in progress. •Tender of ballast supply awarded on 21.12.23 & work is in progress. •Ratangarh - Molisar (18.0 KM) section Commissioned on 31st Jan’25. •Work sanctioned in year 2022-23 •Cost of work Rs. 422.60 Cr. •DPR sanctioned by Railway Board on 03.02.2023. •Civil works Tender for Ratangarh- Molisar (16.69 Kms) is awarded on 13.07.23 & Work is in progress. •Civil Works Tender for Churu- Molisar (26.12 Kms) is awarded on 04.12.2023 & Work is in progress. •P.way Tender for Churu- Ratangarh (42.81 Kms) is awarded on 11.12.2023 & work is in progress. •Tender of ballast supply awarded on 21.12.23 & work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone