Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DOUBLING BETWEEN CHURU-RATANGARH (42.81 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -25

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
422.60422.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
015.6624.7840.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20280/01/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

•Work sanctioned in year 2022-23 •Cost of work Rs. 422.60 Cr. •DPR sanctioned by Railway Board on 03.02.2023. •Civil works Tender for Ratangarh- Molisar (16.69 Kms) is awarded on 13.07.23 & Work is in progress. •Civil Works Tender for Churu- Molisar (26.12 Kms) is awarded on 04.12.2023 & Work is in progress. •P.way Tender for Churu- Ratangarh (42.81 Kms) is awarded on 11.12.2023 & work is in progress. •Tender of ballast supply awarded on 21.12.23 & work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone