Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : DOUBLING BETWEEN REWARI-KATHUWAS (27.73 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -18

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
352.410352.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.3115.6525.43142.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20270/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50130

Ministry Review Date

LatestLastPhysical Progress (%)Status
31Ongoing

Monthly Status

Background Information

•20E of 3.339 Ha land of Rewari distt published on 02.09.2024. Physical land possession is in progress. •20E of 2.761 Ha land of Kotputli-Behror distt (Rajasthan) published on 18.09.2024. 98% physical land possession completed. •Civil works Tender awarded on 24.01.2024. •P-way Tender awarded on 26.04.2024. •Tender of ballast supply awarded on 15.03.2024 Miscell. Balance works tender awarded on 03.10.2024 •Work sanctioned in year 2022-23 •Cost of work Rs. 352.41 Cr. •DPR sanctioned by Railway Board on 03.02.2023. •Tender Discharged due to high rates. Tender for Civil works awarded on 24.01.2024. •Work of Rewari station EI Building in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone