Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-18
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
•20E of 3.339 Ha land of Rewari distt published on 02.09.2024. Physical land possession is in progress.
•20E of 2.761 Ha land of Kotputli-Behror distt (Rajasthan) published on 18.09.2024. 98% physical land possession completed.
•Civil works Tender awarded on 24.01.2024.
•P-way Tender awarded on 26.04.2024.
•Tender of ballast supply awarded on 15.03.2024
Miscell. Balance works tender awarded on 03.10.2024
| •Work sanctioned in year 2022-23
•Cost of work Rs. 352.41 Cr.
•DPR sanctioned by Railway Board on 03.02.2023.
•Tender Discharged due to high rates. Tender for
Civil works awarded on 24.01.2024.
•Work of Rewari station EI Building in progress.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |