•DPR of Devgarh Mandriya-Nathdwara GC with cost Rs. 968.92 Cr. Sanctioned by RB vide letter dated 24.01.2023.Work in progress in yards and at locations of curve easement.
•All Contracts for Civil, S&T and Electrical for NDT-DOHM GC have been awarded.
•Work is in progress. | •Work of Marwar-Mavli (151.65 Km) Gauge Conversion project was sanctioned in year 2017-18 with Cost Rs. 1597.12 Cr.& ROR (-) 5.11%.
•DPR costing Rs.2654.04 Cr. was submitted to Railway Board on 04.12.2017. DPR includes the GC Works from Marwar Jn. to Kankroli and New Line from Kankroli to Nathdwara Town.
•Execution of project kept in abeyance by Railway Board vide letter dated 24.09.2019.
•RB advised to submit revised DPR of Marwar-Mavli GC and keep Marwar-Devgarh as MG Heritage line.
•In compliance of RB observations, fresh DPR of Devgarh Madriya-Nathdwara GC with cost Rs. 968.92 Cr. & ROR (+)2.70% is sent to RB on 04.08.2022.
•DPR of Devgarh Mandriya-Nathdwara GC with cost Rs. 968.92 Cr. Sanctioned by RB vide letter dated 24.01.2023.Work in progress in yards and at locations of curve easement
•Tender for Earthwork, bridge work, station building & Track works for 45 Kms is awarded on 28.07.23 & 2nd tender for balance length is awarded on 05.12.2023.
•Work has started. |