Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : AZIMGANJ-MURSHIDABAD (JIYAGANJ) INCL. RLY. BRIDGE OVER RIVER BHAGIRATHI.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   13.83

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.330187.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
149.3510.05.05159.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20240/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

AZIMGANJ- MURSHIDABAD (JIAGANJ) 6.90 KM: COMMISSIONED ON 29.02.2024 AND DEDICATED TO THE NATION BY HON’BLE PRIME MINISTER OF INDIA ON 02.03.24 AT KNJ, WEST BENGAL.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone