a) Garhwa Road Rail over Rail (Surface Line) (1.5 km) - Section Commissioned on 07.12.2021
b) Garhwa Road Rail Over Rail (ROR Line) Phase - I (4.117 km) - commissioning on 28Mar 25
c) Garhwa Road Rail Over Rail (ROR Line) Phase - II (4.2km) -
Work decided in March 24.
Land Acquisition scope -23.15 acre (20A awaited).
Earth work in available land is in progress. TDC - March 26 | a) Garhwa Road Rail over Rail (Surface Line) (1.4 km) - Section Commissioned on 07.12.2021.
b) Garhwa Road Rail Over Rail (ROR Line)(5.1km) - E/W & Blanketing - Work in progress,
Minor bridges - Completed,
Major Bridges - 04 no Br. completed out of total 05 no Br.&
Track linking - Work in progress,
OHE work in progress.
Targeted month of commissioning in Sept, 2024. |