Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GARHWA ROAD - RAIL OVER RAIL.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
262.710262.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
203.118.564.77226.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

a) Garhwa Road Rail over Rail (Surface Line) (1.5 km) - Section Commissioned on 07.12.2021 b) Garhwa Road Rail Over Rail (ROR Line) Phase - I (4.117 km) - commissioning on 28 Mar 25 c) Garhwa Road Rail Over Rail (ROR Line) Phase - II (4.2km) - E/Work - 45000 out of 160000 cum completed, Work is in progress, OHE work in progress. Issue with state government :- Land acquisition of 27.0954-acre (pending) in Palamu District. Earth work in available land is in progress. TDC - Mar 26a) Garhwa Road Rail over Rail (Surface Line) (1.4 km) - Section Commissioned on 07.12.2021. b) Garhwa Road Rail Over Rail (ROR Line)(5.1km) - E/W & Blanketing - Work in progress, Minor bridges - Completed, Major Bridges - 04 no Br. completed out of total 05 no Br.& Track linking - Work in progress, OHE work in progress. Targeted month of commissioning in Sept, 2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks