Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GARHWA ROAD - RAIL OVER RAIL.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
262.710262.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
114.840.0612.63167.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/07/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

a) Garhwa Road Rail over Rail (Surface Line) (1.4 km) - Section Commissioned on 07.12.2021. b) Garhwa Road Rail Over Rail (ROR Line)(5.1km) - E/W & Blanketing - Work in progress, Minor bridges - Completed, Major Bridges - 04 no Br. completed out of total 05 no Br.& Track linking - Work in progress, OHE work in progress. Targeted month of commissioning in Sept, 2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone