Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GARHWA ROAD - RAIL OVER RAIL.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    23

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
262.710262.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
17626.021.08203.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

a) Garhwa Road Rail over Rail (Surface Line) (1.5 km) - Section Commissioned on 07.12.2021 b) Garhwa Road Rail Over Rail (ROR Line) Phase - I (4.117 km) - commissioning on 28Mar 25 c) Garhwa Road Rail Over Rail (ROR Line) Phase - II (4.2km) - Work decided in March 24. Land Acquisition scope -23.15 acre (20A awaited). Earth work in available land is in progress. TDC - March 26a) Garhwa Road Rail over Rail (Surface Line) (1.4 km) - Section Commissioned on 07.12.2021. b) Garhwa Road Rail Over Rail (ROR Line)(5.1km) - E/W & Blanketing - Work in progress, Minor bridges - Completed, Major Bridges - 04 no Br. completed out of total 05 no Br.& Track linking - Work in progress, OHE work in progress. Targeted month of commissioning in Sept, 2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone