Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GOMOH - FLYOVER FOR DOWN TRAINS.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
487.730487.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
239.81113.9721.86375.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

E/W Filling - Work in progress, E/W Cutting - Work in progress, Blanketing - Work in progress, Minor bridges - 14 nos Br. completed out of total 46 nos Br., OHE work in progress. Work in progress. Gomoh Flyover for DN trains 42 km targeted in Feb 2026. Revised target is due to delay in land acquisition. Issue with state government(s):- • Total land to be acquired – Raiyati land - 89.83 Ha, GM land - 3.34 Ha Total - 93.17 Ha (230 acre in 08 villages). • Rs 4.52 Cr. land payment against GM land of 2.86 acre in favour of DC/Dhanbad deposited in Feb/2024. • Rs 1.152 Cr. land payment against GM land of 1.12 acre in favour of DC/Dhanbad deposited in Mar’24 • Total 218 Acre out of 221 Acre Raiyati land and 8.25 Acre GM land has been handed over by DLAO/DHN and DC/DHN respectively to railway for Gomoh fly over DL Project. • Disbursement of payment not yet completed by State Govt. and partly the matter has been referred to LA court due to which there is local disturbance at work site and so work could not be started on acquired land. Target month of commissioning March 26Gomoh Flyover for DN trains 22km targeted in Sep 2025. Revised target is due to delay in land acquisition. Land handed over on 30.04.2024. Work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone