Gomoh Flyover (22 km) - E/work - 27.666 Lcum out of 46.45 Lcum completed., Minor Br./LHS/RUB - 8 nos br. work in Progress & 32 nos Br. completed out of total 49 nos Br., Major Bridge - Work in progress, ROB - 6 nos Br. work in progress out of total 8 nos Br., OHE work in progress.
Critical Issues along with Action taken – Encumbrance free land acquisition Work in progress. Gomoh Flyover for DN trains 42 km targeted in March 2026. Revised target is due to delay in land acquisition.
Issue :- 221.981-acre land acquisition, paper possession given. But disbursement of payment to land losers yet not complete.
Target month of commissioning March 26 | Gomoh Flyover for DN trains 22km targeted in Sep 2025. Revised target is due to delay in land acquisition.
Land handed over on 30.04.2024.
Work in progress. |