Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GOMOH - FLYOVER FOR DOWN TRAINS.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
686.030487.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
375.649.9213.89399.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

E/W - 26.29 Lcum out of 46.45 Lcum completed, Blanketing - Work in progress, Minor bridges - 28 nos Br. completed out of total 49 nos Br., Major Bridge - Work in progress, ROB - Work in progress, OHE work in progress. Critical Issues along with Action taken – Encumbrance free land acquisition Gomoh Flyover for DN trains 42 km targeted in March 2026. Revised target is due to delay in land acquisition. Issue with state government(s):- 221.981-acre land acquisition, paper possession given but disbursement of payment to land losers yet not completed. Target month of commissioning March 26Gomoh Flyover for DN trains 22km targeted in Sep 2025. Revised target is due to delay in land acquisition. Land handed over on 30.04.2024. Work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks