Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : GOMOH - FLYOVER FOR DOWN TRAINS.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
686.030487.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
375.6423.8120.01419.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

Gomoh Flyover (22 km) - E/work - 27.666 Lcum out of 46.45 Lcum completed., Minor Br./LHS/RUB - 8 nos br. work in Progress & 32 nos Br. completed out of total 49 nos Br., Major Bridge - Work in progress, ROB - 6 nos Br. work in progress out of total 8 nos Br., OHE work in progress. Critical Issues along with Action taken – Encumbrance free land acquisition Work in progress. Gomoh Flyover for DN trains 42 km targeted in March 2026. Revised target is due to delay in land acquisition. Issue :- 221.981-acre land acquisition, paper possession given. But disbursement of payment to land losers yet not complete. Target month of commissioning March 26Gomoh Flyover for DN trains 22km targeted in Sep 2025. Revised target is due to delay in land acquisition. Land handed over on 30.04.2024. Work in progress.