Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : DOMINGARH - GORAKHPUR - GORAKHPUR CANTT - KUSUMHI - 3RD RUNNING LINE (21.15 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   144.95

Time Overrun (Months)-    8

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
186.850457.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
226.04165.535.28396.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/02/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
59.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Feb-25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks