Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : DOMINGARH - GORAKHPUR - GORAKHPUR CANTT - KUSUMHI - 3RD RUNNING LINE (21.15 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
351.030500.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
464.91011.18476.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
59.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

TDC for commissioning of the project July - 25TDC for commissioning of the project Feb-25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks