Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 160.56
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Initially land was to be handed over free of cost by State Govt. of Punjab.
Considering the strategic importance of this project, Railway Board vide letter no. 2009/W-2/NR/SY/3 (3025458) dated 26.04.2024 has intimated that the revised estimate including cost of land be submitted to Railway Board for consideration.
Accordingly, Revised estimate at a total cost of Rs 781 Cr including cost of land (165.69 ha,194 cr.) was submitted to Rly. Bd. on 05.11.2024. Observations of Rly. Bd. received on 14.01.2025 which have been replied on 21.03.2025.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |