| Work of New Line between Lonand & Phaltan (25.982 km) for passenger traffic has been completed and section commissioned in Sept-2019. Work of 4 RUBs and 2 ROBs for elimination of 6LCs is in progress. Contracts for Phaltan-Baramati section earthwork, minor bridges, major bridges, ROB, RUB, etc have been awarded & work is in progress. Phaltan-BRMT Land acquisition status- Till date 200.8735 Ha out of 229.5583 Ha has been acquired (159.183 Ha in PA dist. & 41.69 Ha in STR Dist.) for which an amount of Rs 355.58 Cr has already been paid to State authority till date. Similarly, for Forest land payment of Rs.2.67 Cr. for 9.2955 Ha has also been made to DCF,Pune for PA & STR district. |