Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : FLYOVER AT BILASPUR (KHODRI-ANUPPUR) 10 KM.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
303.590303.59

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0029.8629.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Work completed and commissioned on 23.1.24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks