Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : MORAPPUR-DHARMAPURI.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
358.950358.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
36.332.04.739.07

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20283/20273/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
49.7817.52

Ministry Review Date

LatestLastPhysical Progress (%)Status
1Ongoing

Monthly Status

Background Information

Out of total 36 km length, track to be laid partly on old alignment and partly on new alignment duly acquiring the land from GoTN. Two cases were filed in High Court for ownership of land and got stay order. Revenue department (District Collector, Dharampuri) have been requested on 05.03.19, 06.07.19 & 19.07.19 and being contacted frequently for survey and demarcation of land/identifying Patta land in the railway alignment. 3(2) and 3(1) notifications issued for 60.67 Ha of land (14 villages issued out of 18 villages). 4 villages delayed due to law & order problem.3(2) and 3(1) notifications to be issued.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone