Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-15
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Work for Bridge Nos. EAK 10 and EAK 17 awarded on 14.02.2024. Kumbalam yard work LOA awarded on 03.06.2024 and reach work is to be called. Soil investigation work is in progress. Piling work of Br.No.EAK 10&17-Started. Earthwork resumed. Preparatory works for Kumbalam Yard work Started. Casting of coping slab is in progress(80% completed). Road approach to station building is in progress. Earthwork at doubling and non doubling side is in progress. Pile foundation work of EI building is in progress. Earthwork at the A1 approach of EAK 17 from LC 4 is in
progress. Test pile of EAK 10 has been completed. Casting of coping slab is in progress. Bushes and grass are being cleared for during earthwork between LC 6 and LC 7. Initial pile load test for EAK 10 at A1 approach completed. Earth filling works b/w EAK10 A2 side and EAK 11 is in progress (7000 m3). EAK 17-A1 side filling is in progress and concreting of pile for initial pile load test is scheduled on 05/03/2005. EAK 24 LHS-8 out of piles completed. EAK 24 Doubling side Piling work is in progress. Earth work is in progress (10000 m3). El Building works - completed upto lintel
level of first floor. Preparatory works for Gate lodge(LC6) started | Handing over of land is expected from May 2024. Work of Bridge Nos.EAK 10 & EAK17 have been awarded on 14.02.2024. Tender for Kumbalam yard and reach work is to be called. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |