Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : ERNAKULAM-KUMBALAM - PATCH DOUBLING (7.71 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -20

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
600.82595.39595.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0269.97.01269.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20287/20267/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
101.81.25

Ministry Review Date

LatestLastPhysical Progress (%)Status
.5Ongoing

Monthly Status

Background Information

Handing over of land is expected from May 2024. Work of Bridge Nos.EAK 10 & EAK17 have been awarded on 14.02.2024. Tender for Kumbalam yard and reach work is to be called.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone