Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KUMBALAM-THURAVUR - PATCH DOUBLING (15.59 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    40

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
812.850802.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
258.012.46.15260.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20230/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

The work for construction of Bridge No. EAK 31 is awarded on 14.02.2024. Reach work tender awarded. Piling work of Br.No.EAK 31-Started. TUVR Yard tender awarded. Earthwork is in progress. Assembling of Barges for EAK 31 is in progress. Preliminary survey works have been started. EAK 31- A1 and A2 side pile load test completed. Earthwork of about 2000 m3 completed.8 out of 9 piles completed at A2 side. 6 out of 6 piles completed at Pier 27 side. Earthwork at A1 and A2 side of EAK 31 is in progress. Land work is in progress for KUMM-TUVR doublingHanding over of land is expected from Sep 2024. Work of Br.No. EAK 31 is awarded on 14.02.2024. Yard work and reach work tender to be called.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone