The work for construction of Bridge No. EAK 31 is awrded on 14.02.2024. Reach work tender awarded. Piling work of Br.No.EAK 31-Started. TUVR Yard tender awarded. Earthwork is in progress. Assembling of Barges for EAK 31 is in progress. Preliminary survey works have been started. EAK 31- A1 and A2 side pile load test completed. Earthwork of about 2000 m3 completed.8 out of 9 piles completed at A2 side. 6 out of 6 piles completed at Pier 27 side. Earthwork at A1 and A2
side of EAK 31 is in progress. Land acquisition work is in progress for KUMM-TUVR doubling. Piling
works of Abutment A2 & Pier 26, 27. Earth work b/w 8/000-8/500 is in progress. EAK 31 initial load test is over at A1 side. Total-34/186 piles completed. Soil exploration works of KUMM-TUVR section is in progress. | Handing over of land is expected from Sep 2024. Work of Br.No. EAK 31 is awarded on 14.02.2024. Yard work and reach work tender to be called. |