Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KUMBALAM-THURAVUR - PATCH DOUBLING (15.59 KM).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
812.850802.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
260.6219.777.09287.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

Work for Bridge Nos. EAK 10 and EAK 17 awarded on 14.02.2024. Kumbalam yard work LOA awarded on 03.06.2024 and reach work is to be called.Soil investigation work is in progress. Piling work of Br.No.EAK 10&17-Started. Earthwork resumed. Preparatory works for Kumbalam Yard work Started. Casting of coping slab is in progress(80% completed). Road approach to station building is in progress. Earthwork at doubling and non doubling side is in progress. Pile foundation work of EI building is in progress. Earthwork at the A1 approach of EAK 17 from LC 4 is in progress. Test pile of EAK 10 has been completed. Casting of coping slab is in progress.Bushes and grass are being cleared for duing earthwork between LC 6 and LC 7. Initial pile load test for EAK 10 at A1 approach completed. Earth filling works b/w EAK10 A2 side and EAK 11 is in progress (7000 m3). Filling of Alleppey side approach to EAK 10 is in progress.EAK 17- Earthwork is in progress. Soil exploration of minor bridges and embankment is in progress. EAK 24 LHS-8 out of 8 piles completed. EAK 24 Doubling side-About 75% Piling works completed. Kumbalam yard- Earth filling on doubling side and non doubling side is in progress-50% completed. Preparatory works for Gate lodge (LC 6) started. El Building structure almost completed except roof slab. Subsoil exploration b/w ERS-KUMM incl.major bridges completed. Earth work-A2 approach of EAK 10 is in progress. Earth work at Thirunettur station (base layer) is in progress Earth wk b/w LC 4 to A1 of EAK 17 in progress Test pile at EAK 17 completed. Earth work at KUMM yard b/w CH:7/200-8/000 is in progress. EAK 24-LHS piling completed and RHS-19 out of 24 piles completed. Earth filling works of 33000m3 has been completed in ERS-KUMM section. In KUMM yard- 24000m3 of Earth filling completed. Boundary protection works by sheet pile is in progressHanding over of land is expected from Sep 2024. Work of Br.No. EAK 31 is awarded on 14.02.2024. Yard work and reach work tender to be called.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks