Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-24
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Out of 101.53 Ha Private Land, possession has been taken of 98.60 Ha (97.11%) Private Land. Compensation/Payment by Spl Land Acquisition officer, Aravalli District is in process. Handing over physical possession for balance 2.93 Ha (4 villages) and grant permission to start the work in Govt land. 3.83 Ha.
EPC contract agreement done in Oct.2023. Work started after monsoon. Work is in progress on 11 LHS/RUB. Earthwork is in progress.
TDC : 26.65 Km - March.25 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |