Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NATHDWARA-NEW NATHDWARA NEW LINE ( MM OF AJMER-CHITTAURGARH-UDAIPUR).

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
166.330166.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
8.4347.38055.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks