Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
12
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
(i)Naihati β Kalyani 3rd line (10.37 Km) : Commissioned on 20.03.2023.
Balance Section: (ii)Kalyani β Ranaghat 3rd line (25.17 Km) : Targeted β Marβ26. Physical Progress -15%, The project practically on hold & no work is going on due to dispute in Railway land boundary, owing to number of court cases & several public notices.
General Manager/ER has written a letter on 30.10.2023 to Chief Secretary, West Bengal to verify State Govt old records and carry out necessary corrections in their record as per correct Rly land plan. Meeting with Land Reform & Rehabilitation commissioner on 29.11.2023 & DC/Nadia held on 30.11.2023, 09.02.2024 & 22.03.2024 respectively to sort out the matter. Issue has been flagged in PMG portal also. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |