Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : NAHATI - RANAGHAT 3RD LINE (MM OF KALINARAYANPUR - KRISHNANAGAR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
283.540283.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
135.9314.72.5151.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20253/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.990

Ministry Review Date

LatestLastPhysical Progress (%)Status
44Ongoing

Monthly Status

Background Information

(i)Naihati – Kalyani 3rd line (10.37 Km) : Commissioned on 20.03.2023. Balance Section: (ii)Kalyani – Ranaghat 3rd line (25.17 Km) : Targeted – Mar’26. Physical Progress -15%, The project practically on hold & no work is going on due to dispute in Railway land boundary, owing to number of court cases & several public notices. General Manager/ER has written a letter on 30.10.2023 to Chief Secretary, West Bengal to verify State Govt old records and carry out necessary corrections in their record as per correct Rly land plan. Meeting with Land Reform & Rehabilitation commissioner on 29.11.2023 & DC/Nadia held on 30.11.2023, 09.02.2024 & 22.03.2024 respectively to sort out the matter. Issue has been flagged in PMG portal also.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <