Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : NAHATI - RANAGHAT 3RD LINE (MM OF KALINARAYANPUR - KRISHNANAGAR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
283.540283.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
151.1512.41.4164.95

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20253/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
44Ongoing

Monthly Status

Background Information

Naihati – Kalyani 3rd line (10.37 Km) :Commissioned on 20.03.2023. Balance Section: Kalyani – Ranaghat 3rd line (25.17 Km) : Targeted in 2025-26. Physical Progress -15%. The Project is practically on hold & no work is going on due to dispute in Railway land boundary, owing to number of court cases & several public Notices. General Manager/ER has written a letter on 30.10.2023 to Chief Secretary, West Bengal to verify State Govt old records and carry out necessary corrections in their record as per correct Rly land plan. Meeting with Land Reform & Rehabilitation commissioner on 29.11.2023 & DC/Nadia held on 30.11.2023, 09.02.2024 & 22.03.2024 respectively to sort out the matter. Meeting with ADM/Nadia held on 15.07.24 to sort out the issue. Issue has been flagged in PMG portal also. Meeting with Secretary/Land Reforms & Rehabilitation Commisinoner done on 06.08.2024, with Transport Secretary on 28.11.24, with ADM/LR/Nadia on 02.12.24 & 19.12.24 and with Addl. Secretary/ Land /WB on 17.12.2024 regarding correction of ROR. CALA has been appointed by State Govt on 02.01.2025. Recently a meeting held with Chief Secretary, WB & General Manager, ER for early correction of Land Records. Last PMG meeting on this subject was held on 21.03.2025 where State has ensured for correction of land records by June’2025.(i)Naihati – Kalyani 3rd line (10.37 Km) : Commissioned on 20.03.2023. Balance Section: (ii)Kalyani – Ranaghat 3rd line (25.17 Km) : Targeted – Mar’26. Physical Progress -15%, The project practically on hold & no work is going on due to dispute in Railway land boundary, owing to number of court cases & several public notices. General Manager/ER has written a letter on 30.10.2023 to Chief Secretary, West Bengal to verify State Govt old records and carry out necessary corrections in their record as per correct Rly land plan. Meeting with Land Reform & Rehabilitation commissioner on 29.11.2023 & DC/Nadia held on 30.11.2023, 09.02.2024 & 22.03.2024 respectively to sort out the matter. Issue has been flagged in PMG portal also.