Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KARAIKAL PERALAM(23KM)-NEW LINE PROJECT.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
304.220373.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
202.9123.9755.7282.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20263/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
106.170

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

All works in the section completed and Engine Rolling successfully completed on 26.03.2025. Awaiting CRS Inspection.Earthwork, blanketing, bridge works and track linking are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks