Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KARAIKAL PERALAM(23KM)-NEW LINE PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   22.75

Time Overrun (Months)-    -9

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
304.220373.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
202.9163.497.84274.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20263/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
285.08167.58

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

Earthwork and Blanketing completed. Track Linking completed with Service Rails. Works are in Final Stages of Completion. TDC: Mar-2025.Earthwork, blanketing, bridge works and track linking are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone