Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : NAGAPATTINAM THIRUTURAIPUNDI (38KM)- NEW LINE PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   16.38

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
677.120788.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
103.1839.260142.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20263/20273/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
285.08167.58

Ministry Review Date

LatestLastPhysical Progress (%)Status
19Ongoing

Monthly Status

Background Information

Due to poor soil condition , the earthwork in formation has to be done with PVD in stages duly providing consolidation time. Agency for 6 out of 10 reaches available and works are in progress.Tender for Station Building, ROB, Ballast and Track Linking to be called. This section is targeted for completion by Mar-2027.Agencies are being finalised for balance reaches of earthwork.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone