Due to poor soil condition , the earthwork in formation has to be done with PVD in stages duly providing consolidation time.
Agency for 6 out of 10 reaches available and works are in progress.Tender for Station Building, ROB, Ballast and Track Linking to be called. This section is targeted for completion by Mar-2027. | Agencies are being finalised for balance reaches of earthwork. |