Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : KOLKATA METRO RAIL CORPORATION LIMITED.
Project Name : EAST WEST METRO CORRIDOR KOLKATA.

Reported Date : 09-APR-24

MOU Status :

Monthly Report : 3 / 2024

Cost Overrun (%)-   114.22

Time Overrun (Months)-    93

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4874.58010442.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0286.490286.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20160/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone