Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : Maharashtra Rail Infrastructure Development Corporation Limited.
Project Name : NAGPUR- NAGBHIR RAILWAY LINE GAUGE CONVERSION PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   70.21

Time Overrun (Months)-    16

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
140002383

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1014.25561.94106.671682.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/010/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
490.220

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone