Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
2.7069 Ha of land acquisition involved in Kalipahari-Bakhtarnagar 5th line work. Application for nomination of CALA has been submitted on to State Government on 22.07.24. ADM (LR), Paschim Bardhaman has been nominated as CALA vide Spl. Secy. to Govt. of WB’s letter dt.07.01.2025. Gazette Notification regarding nomination of CALA U/S 7A published on 13.01.25. Application for land acquisition submitted to CALA on 19.02.2025. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |