Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : SITARAMPUR BYE - PASS LINE (6.59 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
461.640461.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12.4412.11.325.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
223.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

•The work for construction of EI building at Barachak in progress (40% completed). Work for U-trough in progress – 280/1466 completed. • Construction of Test pile for horizontal and vertical load is in progress. • Fabrication of girders for viaduct is in progress (50/188 completed). • Electrical infringement removal in progress. There are 21 nos. infringements. 3 no 220 KV of DVC, 1 no 220 KV of WBSETCL. 2 no 33 KV of IPCL 5 no 33 KV of WBSEDCL 2 no 11 KV of WBSEDCL. 4 no 11 KV of IPCL. 2 no LT Line of WBSEDCL 2 no 11 KV of RLY. TDC for removal of electrical infringements – 31.12.2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks