Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SONAPUR TO GUWAHTI (AS-3).

Reported Date : 10-SEP-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    149

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2450174.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
225.6514.710240.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20080/08/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17.617.6

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone