Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : KALGHAT-MP/MAHARASHTRA BORDER KM 16.6-84.70.

Reported Date : 04-JUL-11

MOU Status :

Monthly Report : 5 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5490549

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
489.2325.80815

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20100/05/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone