Reported Date :
26-DEC-22
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
12
/
2022
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
117
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
2783.05 | 153.95 | 13.59 | 2950.59 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
The 6 - laning of Pune - Satara Section of NH-4 was approved on October 2010 with Capital Investment of Rs. 1724.55 Crores with schedule completion date March 2013.Present Physical progress is 97.48%. Out of 140.35 kms only 137.66 kms work has been completed. PCOD has been issued on dt. 30.04.2022. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |