Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : PUNE-SATARA(NH-4).

Reported Date : 26-DEC-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    117

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1724.5501724.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2783.05153.9513.592950.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/012/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.49Completed

Monthly Status

Background Information

The 6 - laning of Pune - Satara Section of NH-4 was approved on October 2010 with Capital Investment of Rs. 1724.55 Crores with schedule completion date March 2013.Present Physical progress is 97.48%. Out of 140.35 kms only 137.66 kms work has been completed. PCOD has been issued on dt. 30.04.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone